The Project involves the design and construction of 1,007 student units constructed over 5 Blocks (Section 1: Blocks 1,2 and 3, Section 2: Blocks 4 and 5). The overall scheme incorporates communal facilities including, lounge/study and lounge/games room and associated external works.
Highlights
Occupying a prime location just a 4 minute walk to Liverpool University and within a 1 mile radius to all other Liverpool Universities.
Herbert T Forrest Limited was originally appointed as the Main Contractor to undertake the works, however after entering administration, Vermont had been appointed as the current Main Contractor to complete the remaining works, including undertaking any necessary corrective / remedial works.
Works are due to complete on the first phase in August 2021; with the second phase completing in 2022.
Location: Liverpool
Sector: Student Accommodation
Programme: 2020 to current
Procurement: Single Stage Design and Build – Negotiated
Services: Cost Management
Key Facts
1007 units
Communal space